SCHOOL PROJECT

Construction Information

 

Building a school in rural sections of Petit-Goave, Haiti is a challenging endeavor. We have to deal with rocky terrain, mother nature, the lack of electricity,  lack of water and security. We have  made noticeable progress in the last few months, but there is still plenty of work to be done to complete the school

 

Phase 6:  In Progress

  • Roofing and flooring
  • Electrical work
  • Doors and windows
  • Furnishing

 

Completed Phases

Phase1: Complete

  • Commitments
  • Calculation (Operating and maintenance Cost)
  • Preliminary Design (Indoor and outdoor space requirements)
  • Location

 

Phase 2: Complete

  • Schedule Defined
  • Tasks and Responsibilities
  • License granted
  • Agreement Signed

 

Phase 3: Complete

  • Blueprint - Design and Drawings begin
  • Define how building will look
  • Construction plan accepted and construction to begin

 

Phase 4: Complete

  • Purchasing of materials (Sand, gravel, water, iron bars, rocks..etc)
  • Investment in local economy
  • Hire local workers
  • Foundation Started

 

Phase 5: Complete

  • Removal of heavy rocks
  • Digging and laying of iron bars
  • Removal of dirt
  • Smooth of Walls and floor
  • Installment of Electricity
  • Doors and windows

 

 

MORE ABOUT US

GET EDUCATED

OUR PROJECTS